MUNICIPAL CORPORATION OF BRIHAN MUMBAI
K/EAST WARD (LOT-7)
Slum Sanitation Programme
Progress Report for February 2005
Date
of Report: February 2005.
|
Sr.
No./ Wd. No.
|
Name
of Sites
|
W.O.
No. & Date
|
Date
of Starting
|
Expected
date of Completion
|
D/R
or New
|
CBO
formation A/c
|
Water
Connection
|
Electric
Connection
|
Status
of Work
|
Amount
paid in %
|
Remarks
|
|
|
|
|
|
|
|
CBO
formed
|
CBO
A/c.
|
Joint
A/c.
|
|
|
|
|
|
|
1
|
Janta Colony, Prem Nagar, Jogeshwari, KE/122/010,
12 seated,
S.L., Existing 12 Seats
|
4377/
02.02.2001
|
21.04.2001
|
31.03.2002
|
D/R
|
Yes
|
Yes
|
Yes
|
No
|
No
|
Completed
Stage-III
|
85%
|
|
|
2
|
Near
St.
Mary
School
, Janta Colony, KE/126/001,
16 Seated,
S.L., Existing 10 Seats
|
-"-
|
21.05.2001
|
31.03.2002
|
D/R
|
Yes
|
Yes
|
Yes
|
No
|
No
|
Completion
Stage-III
|
70%
|
Drainage
connection balance.
|
|
3
|
Shri Ramnagar, near Shradhanand, KE/039/002,
12 Seated,
A.P., Existing 8 seats
|
-"-
|
22.06.2001
|
31.03.2002
|
D/R
|
Yes
|
No
|
No
|
Yes
|
No
|
Commissioned
Stage-IV
|
95%
|
MOU
pending. Commissioned on 23.02.2003.
|
|
4
|
Sambhaji
Nagar,
W.E. Highway
, Vile Parle (E), 056/001,
10 Seated,
S.L., Existing 10 seats
|
9168/
14.03.2001
|
25.05.2001
|
28.02.2002
|
D/R
|
Yes
|
No
|
No
|
Yes
|
No
|
Commissioned
Stage-IV
|
85%
|
Commissioned
in March 2004.
|
|
5
|
Utkarsha
Nagar, Andheri (E), 065/007 & 008, 19 Seated, SL, Existing
16 seats
|
-"-
|
31.05.2001
|
30.04.2002
|
D/R
|
Yes
|
No
|
No
|
Yes
|
No
|
Commissioned
Stage-IV
|
85%
|
Commissioned
in January 2004.
|
|
6
|
Shyam
Nagar, Jogeshwari (E), KE/117/013 & 014,
14 seated,
A.P., Existing 6 Seats
|
3940/
09.08.2001
|
21.04.2001
|
30.06.2002
|
D/R
|
No
|
Yes
|
Yes
|
No
|
No
|
Commissioned
Stage-IV
|
95%
|
Commissioned
on 02.06.2002 without MOU.
|
|
7
|
Tripathi
Nagar,Jog(E),
15 Seated,
S.T., Existing open plot
|
-"-
|
15.06.2001
|
30.06.2002
|
New
|
Yes
|
Yes
|
Yes
|
Yes
|
No
|
Commissioned
Stage-IV
|
95%
|
Commissioned
on 16.08.2002 without MOU.
|
|
8
|
Azad Hindustan Nagar, Goni Nagar, Jog. (E), KE/137/007,
12 Seated,
S.T., Existing 8 Seats
|
3940/
09.08.2001
|
01.11.2001
|
30.04.2002
|
D/R
|
Yes
|
No
|
No
|
No
|
No
|
Commissioned
Stage-IV
|
85%
|
Street
connection, water connection balance.
MOU pending.
|
|
9
|
Baman
Wada, Andheri(E), 189/004, 16 Seated, S.T., Existing 8 Seats
|
-"-
|
13.08.2001
|
28.02.2002
|
D/R
|
Yes
|
Yes
|
Yes
|
Yes
|
No
|
Commissioned
Stage-IV
|
95%
|
Commissioned
on 05.06.2002 without MOU.
|
|
10
|
Ganeshpada,
Andheri (E), KE/181/001,
17 Seated,
S.T., Existing 8 Seats
|
3940/
09.08.2001
|
13.08.2001
|
28.02.2002
|
D/R
|
Yes
|
No
|
No
|
Yes
|
No
|
Commissioned
Stage-IV
|
95%
|
Commissioned
on 08.06.2002 without MOU.
|
|
11
|
Islampura,
Chakala, Siddhivinayak Mandal, Andheri (E), KE/198/004, 005
& 006, 30 Seated, A.P., Existing 10 Seats
|
-"-
|
01.11.2001
|
30.04.2002
|
D/R
|
Yes
|
No
|
No
|
No
|
No
|
Completion
Stag-III
|
70%
|
Completed
without electric, water & overflow connection.
|
|
12
|
Kantilal
Compound, Pump House, Andheri (E), KE/141/005 & 006, 20
Seated, S.T., Existing
|
8034/
14.02.2001
|
15.04.2002
|
|
D/R
|
No
|
No
|
No
|
No
|
No
|
Commissioned
Stage-IV
|
95%
|
No water
& electric connection. u/a commissioned on 27.07.2003. No
CBO formation.
|
|
13
|
Durga
Rahiwasi Sangh, Mahakali Caves Rd,Andheri(E), 12 seated, A.P.,
Existing 8 seats
|
8036/
14.02.2001
|
24.01.2002
|
31.07.2002
|
D/R
|
Yes
|
Yes
|
Yes
|
No
|
No
|
Commissioned
Stage-IV
|
95%
|
Caretaker
room not yet constructed.
Outlet of A.P. tank not connected to S.W.D.
Commissioned in June 04
|
|
14
|
Das Chawl,
Navtarun Mitra Mandal, Opp.
Hema
Ind.
Estate, Jog (E), 15 Seated, S.L., Existing 8 Seats
|
-"-
|
03.01.2002
|
31.07.2002
|
D/R
|
Yes
|
Yes
|
Yes
|
Yes
|
No
|
Commissioned
Stage-IV
|
85%
|
Commissioned
on March 2003 without MOU.
|
|
15
|
Indira
Nagar Rahivasi Sangh, Jog. (E),KE/ 134/001,16 Seated, A.P.,
Existing 8 Seats
|
-"-
|
03.01.2002
|
31.07.2002
|
D/R
|
Yes
|
Yes
|
Yes
|
No
|
No
|
Commissioned
Stage-IV
|
95%
|
Suction
tank not constructed, excess plinth height. Commissioned on
Sept 2003
|
|
16
|
Pitale
House Rahiwasi Sangh,
Hanuman Road
, Vile Parle (E), 6 Seated, S.L., Existing 8 Seats
|
-"-
|
08.01.2002
|
31.07.2002
|
D/R
|
No
|
No
|
No
|
No
|
No
|
Commissioned
Stage-IV
|
|
UG tank
not yet constructed & caretaker room not provided. Water,
Electric, Street connection balance.
|
|
17
|
Sariput
Nagar, Ekta Manch,
J.V. Link Road
, Jog.(E), KE/101/006,
14 Seated,
S.T., Existing
|
-"-
|
02.04.2002
|
|
D/R
|
No
|
No
|
No
|
No
|
No
|
Completion
Stage-III
|
40%
|
Defective
RCC work. Finishing
work is in progress.
|
|
|
TOTAL
|
17
|
|
|
|
|
|
|
|
|
|
|
|
|
Sr.
No.
|
Lot
No. / Ward
|
Contractor's
Name
|
No.of
W.O. in hand
|
No.
of W.O. started
|
Status
of Progress
|
|
|
|
Water
Conn.
|
Elec.
Conn.
|
No.
of Seats
|
Remarks
|
|
|
|
|
|
|
Stage-I
Plinth
|
Stage-II
Roof
|
Stage-III
Completion
|
Stage-IV
|
CBO
formed
|
CBO
A/c
|
Jt.
A/c
|
Yes/No
|
Yes/No
|
|
|
|
1
|
Lot-7
|
M/s. SPARC
|
17
|
17
|
0
|
0
|
4
|
13
|
17
|
8
|
8
|
8/9
|
7/10
|
ST-
94 AP-84
SL-78
|
Jt.
A/c. not opened in 9 cases.
|
|