|
Bombay Dyeing proposal for P. Budkar Marg ALM
A) The Concept:
The self sustainable model is designed utilizing
the rag pickers in an organized manner to collect and segregate
dry & wet waste whereby the dry waste is sold and generates
revenue and wet waste is initially handed over the MCGM but later
as the initiative gets the support of the community the wet waste
is pulverized and placed in vermin-composting pits and recycled
into soil which can be sold as manure.
B)
Location of the Initiative:
Pandurang
Budhkar Marg:
Area includes the footpath opposite Elphinstone Mill, round
the corner, either side of Deepak Talkies footpath and the approach
road to Bombay Dyeing Mills all the way down to Worli Naka.
Site
Plan as per Annexure A.
C)
Present Scenario:
Presently
at PB Marg is facing the following issues;
1)
Lot of visible waste spread over the street,
2)
Vagrant
Vagabonds occupying the footpaths making pedestrian use difficult
3)
Lack
of sanitation on either side of road on account of squatting by
these vagrants & vagabonds,
4)
Absence
of public toilet in close proximity of slums main reason for squatting,
5)
Large
amount of parking in a no parking zone detrimental to cleanliness
6)
Beautification
programme undertaken not well maintained.
Photos
as per Annexure B.
D)
Initiatives Planned:
1)
Garbage collection in the area identified:
1.
Maintaining
the community bin area to ensure that the garbage is dumped in the
bin and not around it.
2.
Garbage
Collection & segregation
3.
Communication
of garbage segregation within the slum area.
4.
Collection
of waste from the slum dwellings
5.
Ensure
timely removal of garbage from the bin area.
6.
Placement
of ragpickers for six months to ensure the community bin area is
kept clean
7.
Beautification
of the community bin area.
8.
Printed
communication in three languages (Hindi and Marathi) that clearly
mentions the process of garbage collection and the timings for the
garbage collection.
9.
Secretaries
from each building to be handed over the communication of the initiative.
A lead time of 15 days to be given before the process comes into
effect.
10.
Printed
material will be printed by Bombay Dyeing and will be communicated
as a social initiative undertaken by BDMC and MCGM.
11.
BDMC
to provide a tricycle and uniforms to all the ragpickers in this
area at no cost to the contractor or MCGM
The association through their volunteers will:
12.
Collect
garbage from society gate which needs to be segregated
13.
Training
of the building sweeper to collect the waste from the building in
two separate bins
14.
The
association will also be involved in maintaining composting bins
which can be used to recycle wet garbage from the societies.
2)
Public toilets:
1.
There
is currently a public toilet built just opposite
Paragaon Center but in the vicinity of the slums
there are no public toilets hence squatting on the road has resulted
lot of filth resulting difficulty to the pedestrians. There is a
need to have a public toilet in that vicinity.
2.
A
portable Public toilet can be maintained by us to provide the sanitation
facilities to the slum dweller maintained by the association
3.
The
structure for the same can be provided by MCGM.
F. Participation from MCGM
1.
Notice
to every residential society and commercial establishment for segregation
& collection of garbage by Triratna Prerana Mandal,
2.
Location
to be given by the MCGM for segregation kiosk and pulverizing machine,
3.
Construction
of Kiosks for segregation of waste, pulverizing machine & equipments,
4.
Providing
electricity & absorbing cost at the site for the pulverizing
machine,
5.
Assistance
in creation of the vermi-composting bins,
6.
Assist
the rag pickers in removal of wet garbage. Co-ordination to be worked
out between the MCGM officers and BDMC,
7.
Removal
of vagrant/vagabonds from the Century Mill wall compound and hawkers/
squatters around the crossroad. Create a hawker-free road,
8.
Construction
of footpaths / walkways along Pandurang Bhudkar Marg,
9.
Removal
of taxi parked in the non-parking zone and shifting Taxi stand from
the Pandurang Budhkar Marg,
10.
Identification
of a public toilet in a strategic location in the areas adopted
or look at the option of identifying an island within the vicinity
for beautification,
11.
Providing
water connection & absorbing cost for the water supply at the
Public toilet and for maintaining greenery,
12.
Allowing
beautification of the areas adopted under the initiative,
13.
Providing equipments for the initiative,
14.
Requirement of Notice Boards at 3 different locations,
15.
Pots at different locations approx. 70 nos
G. Other
Agencies involved with their roles:
Name of the Agency involved:
Triratna Prerna Mandal:
i)
Providing gainful employment to slum dwellers,
ii)
Collections, segregation of waste,
iii) Sale of recyclable dry waste,
iv) Vermi-composting of wet
waste,
v)
Maintaining Greenery,
vi) Sale of Compost.
H) Ultimate Objective:
To ensure zero garbage collection by MCGM from the
Location.
“Make My Mumbai Beautiful” Project For Clean Environment
in Mumbai
By Wadia Group & MCGM
Chapter 1: Rationale
for the project:
Mumbai as a city has
faced various issues & problems and numerous efforts have been
made by the MCGM, NGO’s, ALM’s all around the city but more effort
is required to have a cleaner and healthier environment for the
Mumbaitees. In order to bridge the efforts made by the MCGM, NGO’s
& ALM’s , Wadia Group as a responsible corporate citizen contributing
to the well being of the society would like to come ahead to put
in concentrated efforts on area specific basis to improve the well
being of the Mumbaitees.
Chapter 2: Project
Objective & Initiatives Planned
To provide healthy
environment to the people of Mumbai by undertaking various initiatives
for the community in partnership with MCGM that improves the life
of the community and to achieve the same following initiatives are
planned to be executed;
- Cleanliness
Initiative,
- Awareness,
- Road
Beautification,
- Road
Improvement Initiative.
- Public
toilets.
Chapter 3: Process of Execution of Initiative
A) Principles for execution of each initiative
- Each
initiative to be executed as a separate project
- Each
initiative to have separate leader to be co-ordinated by a single
Project Head,
- Goals
for each Initiative planned to be divided into milestones
- Initiatives
to be executed location wise,
- Commencement
of execution for each initiative should be from a small location
say a street and then expanded – No big bang approach,
- Each
execution team should have a monthly review on the milestones
jointly by the MCGM and the WG,
- Any
work done under the entire project should be executed only after
MCGM’s concurrence.
B) Steps for execution of the Project:
Step 1: Identification of the Location
Step 2: Mapping of the requirements
Step 3: Planning of the Initiative
Step 4: Setting up a team of execution
Step 5: Commencement of Execution
Step 6: Review of the Initiative
Step 1: Identification of the Location:
The location for the
each initiative has to be identified by the Governing body for the
entire project constituting Ness
Wadia & Mr Subrat Ratho (Addl. Municipal Commissioner). Presently
the location chosen is Worli where Wadia Group can be more effective
Step 2: Mapping
of the Requirements
For each location
the requirements need to be mapped by the project administration
team. The project administration team would visit the sub locations
identified and list out which are the initiatives required for achieving
the Project objective in that street. For mapping the requirements
form as per Annexure A needs to be filled by the Project Execution
Team.
Step 3: Planning
of the Initiative
For each requirement’s
as mapped as per Annexure A the Initiative needs to be identified
by the Project Administration Team in consultation with the MCGM-
Co-ordinator. Execution methodology for each initiative as selected
have to planned as per Annexure B by the Project Administration
Team (PAT) and has to present it to the Project Co-ordinator and
MCGM Co-ordinator for approval. After approval MCGM Co-ordinator
would call a meeting of the Ward officers and concerned parties
at the sub location to finalize the execution methodology. Each
plan as finalized would have targets or milestones to decide the
achievements.
Step 4: Setting up a Team for execution
Project Administration Team (PAT) to mobilize
the Project Execution Team (PET) whereby third parties (NGO’s, ALM’s,
Contractors, Other Corporate, etc) can be involved for the execution
of the plan as finalized and set up a team for the execution of
the initiative which would closely monitored by the Project Administration
Team.
Step 5: Commencement of the Execution
PET to commence the execution of the Initiative
as planned and report on a monthly basis to PAT the targets achieved.
Step 6: Review of the Initiative
The Project Administrator Team to report on a
monthly basis to the Governing Body as per Annexure C.
C. Milestones for Execution of the Project
|
Milestones
|
Action
|
To
be done by
|
Criteria
& Guidance
|
|
1
|
Identification of location
|
GB
/ PAT
|
Effectiveness
of Team
|
|
2
|
Subdivision of locations
|
PAT
|
Subdivision
on the basis of streets
|
|
3
|
Survey
|
PAT
|
Utilizing
locational plans & Photographs in different time zones.
|
|
4
|
Mapping of Requirements
|
PAT/PET
|
Locational
requirements as per the initiative identified.
|
|
5
|
Plan to fulfill the requirements
|
PAT/PET
|
To
include the requirement, initiative planned and cost of execution
as per Annexure B.
|
|
6
|
Concurrence of MCGM
|
MCGM
|
From
MCGM Co-ordinator and MCGM team at Ward level
|
|
7
|
Setting up team to execute
|
PET
|
|
|
8
|
Commencement of Execution
|
PET
|
|
|
9
|
Review of each initiative
|
PAT
|
As
per Annexure C
|
|
10
|
Review of Project
|
GB
|
As
per Annexure C
|
- Approval
Methodology
For each sub-location
separate budget has to be made as per the requirement mapped as
per Annexure A and initiative planned and approval has to be sought
from the Project Administrator Team and final approval from the
Governing Body.
All approvals have
to be sought on a monthly basis from the Governing Body as per Annexure
B.
Chapter 4: Organization Chart its Aim & functions

Chapter 5: Funding Methodology
In order to fund the project following methodology
should be utilized;
a)
Sponsorship by a Corporate,
b)
Contribution from MCGM,
c)
Sale
of Garbage & other Garbage disposal methodology,
d)
Annual Festivals,
e)
Sports & other social events,
f)
Fines for Nuisance creators,
g)
Public Towing Co,
h)
Advertisements.
Chapter 6: Contribution from the Wadia
Group & MCGM
A) Contribution from the Wadia Group
a)
Management Structure,
b)
Management Support for the entire project,
c)
Corporate Sponsorship,
d)
Co-ordination in participation of enlightened citizens
in Awareness drives.
B) Contribution from MCGM:
I) Location
Contribution:
a)
Permission & Location from kiosks, pulverizing
machines & public toilets,
b)
Infrastructure facilities namely water, electricity
& implements,
c)
Removal of vagrants & vagabonds,
d)
Construction of footpaths/walkways,
Contribution
would vary from sub-location to sub-location hence the contribution
can be approved by MCGM at the time of approval for project execution
plan as per Annexure B.
II) Permanent
Contribution:
a)
Co-ordination between MCGM & teams under the project,
b)
Assistance as per various schemes of MCGM,
c)
Advertisement spaces for the project,
d)
Assistance in implementation of road rules,
e)
Assistance in implementation of the project.
Chapter 7: Project Numbering Methodology:
Each project should be numbered in the following
manner;
|
Location
Roman
Numerals
|
Sub
Location
Numbers
|
Initiative
Alphabets
|
Activity
Small
numbers
|
|
Worli as I
|
PB Marg as 1
|
Cleanliness
A
Awareness
B
Roads
C
Public Toilet
D
|
Garbage removal
as (i)
|
|
Hence a Garbage
removal under cleanliness initiative at PB Marg would be numbered
as I.1.A(i).
|
Annexure
A
Mapping
of Requirement
A. Project Number
:
B. Location Address
:
C. Brief Description of the location
:
D. Location Survey Plan
:
E. Photos of the Location
:
F. Initiative
:
|
Initiative
|
Present
Status
|
Requirement*
|
|
a) Cleanliness
|
|
|
|
b) Awareness
|
|
|
|
c) Road
|
|
|
|
d) Public Toilets
|
|
|
(* Requirements should be in tangible
format to achieve the aim of the initiative in the location).
Annexure
B
Project
Execution Plan
1. Project Number
:
2. Location Address
:
3. Initiatives Planned
:
A) Cleanliness
B) Awareness
C) Roads
D) Public Toilets
4. Resources Required
:
5. Participation from MCGM
:
6. Activity Chart
:
7. Annexure
i) Photos
ii) Locational Plan
Approval by:
a)
Project Administration team:
b)
Governing Body
Annexure C
Template
for Review of Project as on ____/12/2005
A. Project Number
:
B. Location Address
:
C. Activity
Review Chart
:
|
Sr.no
|
Activity
|
Team
|
Date
|
Date
of Execution
|
|
|
|
|
|
|
D. Financials
1. Cost Incurred
|
Sr.no
|
Initiative
|
Amount
(Rs)
|
|
A
|
Cleanliness
|
|
|
B
|
Awareness
|
|
|
C
|
Roads
|
|
|
D
|
Public Toilets
|
|
|
|
Total
|
|
2. Source of amount spent till date:
|
Sr.no
|
Source
of Funding
|
Amount
(Rs)
|
|
A
|
Corporate Sponsorship
|
|
|
B
|
Contribution from MCGM
|
|
|
C
|
Garbage disposal
|
|
|
D
|
Fines
|
|
|
E
|
Public Towing Co.
|
|
|
F
|
Annual Festivals
|
|
|
G
|
Sports Events
|
|
|
H
|
Advertisements
|
|
|
|
Total
|
|
|